There are two pieces of news on downtown Clarendon Hills this fall. Sparrow Coffee announced a soft opening for Wednesday, Oct. 21, in the former Starbucks space at 100 Park Ave. And on Sept. 21, the Village Board approved a smaller version of the Prospect Avenue streetscape project.
The streetscape vote matters more over the long run. The decorative parts of the plan were cut. What the board kept is mostly hardware for running the street on event nights: a power hookup for the stage, permanent barriers at both ends, and more sidewalk on the west side. Prospect Avenue will look much as it does now and will be easier to close for events.
The corner that took an extra year
Sparrow Coffee joined three units into one to build its cafe on Park Avenue, according to Patch. It is also an expensive project by village standards. Sparrow is receiving a $622,000 subsidy from the village's tax increment financing district. A TIF puts growth in property tax revenue back into the district, and the higher tax income is expected to pay back the subsidy.
The timeline ran long. Under the original subsidy agreement, the cafe was due to be ready by last Halloween. After a couple of extensions, the deadline moved to this Halloween, and the announced Oct. 21 date beats it by about 10 days. At last month's Village Board meeting, owner Chris Chacko told officials the space would be where "great architecture meets craft coffee," and said the wait was worth it "because we did it correctly," Patch reported.
Sparrow said it would start with limited hours, 7 a.m. to 1:30 p.m. every day. The company already runs a cafe in Naperville and a roastery in Chicago, so the Clarendon Hills cafe is its second.
Sparrow's slow build-out also came up in the streetscape debate. At the July 20 board meeting, several residents asked the village to hold off on the project until Sparrow was fully operational and a new traffic study had been done during the school year and in bad weather. Others raised concerns about removing the crosswalk near Brama and Sparrow. The meeting minutes record both concerns. Brama is Brama La Pizza at 34 S. Prospect Ave., which has served pizza, sandwiches and salads since 2017.
How $1.2 million became $3.3 million, then $1.9 million
This past April, the village estimated the downtown project at $1.2 million. That is the figure most people heard this summer. By July, the contract in front of the board was capped at $3,256,060 plus a 5% contingency, almost three times the April estimate. Staff said the increase came from the changed design, inflation, and added irrigation, lighting and electrical work.
The July contract also waived competitive bidding, which takes a two-thirds vote of the trustees. The vote was 3–3, so it failed, as Patch reported the next day.
Staff brought back a cheaper version eight weeks later. The September contract names Burke LLC of Rosemont as construction manager, with a guaranteed maximum price of $1,897,877 plus a 5% contingency. The contract is dated Sept. 21, 2026, and lists July 15, 2027, as the substantial completion date. The approved price is about $1.36 million less than the July contract, and about $700,000 more than the April estimate.
Bidding was still waived. In the Sept. 14 staff memo, Village Manager Paul Dalen explained why. Burke had already gathered competitive pricing from three general contractors, chosen for their record of finishing suburban downtown projects quickly and keeping disruption to businesses low. The memo says the downtown is "too important to be left to whomever offers the lowest price."
What was cut and what stayed
The same staff memo lists exactly what came out of the July plan and what the approved project includes.
| Element | Status in the Sept. 21 scope |
|---|---|
| Changes to the Sloan Triangle | Removed |
| Pavers in the roadway | Removed |
| Zero-grade, curbless design | Removed |
| New light poles and string lights | Removed |
| Wider sidewalk on the west side of Prospect | Included |
| New brick pavers on the west side, Park Avenue to Railroad | Included |
| Rebuilt planters at Railroad and mid-block; new planters at Park Avenue | Included |
| Electrical drop at the north end for stage power | Included |
| Removable bollards at the north and south ends | Included |
| Outdoor dining in parking stalls | Eliminated |
Almost everything that would have changed how Prospect looks on a normal Tuesday was removed. A curbless street, pavers across the roadway, new light poles and string lights are what make a street look like a plaza, and none of them survived. Most of what stayed matters on event nights.
The memo spells out what the two event items are for. The north-end electrical drop means a stage at that end of the street no longer needs a generator. The removable bollards at both ends will keep vehicles off the street during special events, so the village no longer has to park dump trucks there, which the memo says will also look nicer. Anyone who has gone to a summer concert or the Holiday Walk downtown has seen the current arrangement.
The change regular customers will notice most is the outdoor dining. Setups in the parking stalls go away, and the west sidewalk from Park Avenue to Railroad gets wider and gets new brick pavers. The brick stayed on the sidewalk and came off the roadway. Residents in July had asked the village to rethink brick pavers because of higher upkeep costs and possible drainage problems.
One more holiday season on the current setup
With a completion date of July 15, 2027, the new hardware isn't scheduled to be in place for this year's events. The village has not published a construction start date. Here is what's ahead downtown:
- Saturday, Oct. 31: Trick-or-treating, 3 to 7 p.m., on the village calendar.
- Saturday, Dec. 5: The Clarendon Hills Chamber of Commerce Holiday Walk, 4 to 8 p.m. Shopping at local merchants starts at 4 p.m. and the tree lighting in front of Village Hall is at 5 p.m. The Chamber also lists horse-drawn wagon rides, roasted chestnuts and refreshments.
- During the Holiday Walk: The Chamber's posted schedule has Santa and the Clarendon Hills Park District elves at the Village Triangle from 5:30 to 8 p.m., and Anna and Elsa from Frozen at Burlington Plaza from 4:15 to 7:15 p.m. The schedule page is still titled 2025, so check the times with the Chamber closer to the date.
The Chamber's Holiday Walk page also has a printable map of merchant specials. This year, Sparrow on Park Avenue will be on the route for the first time.
Holiday Walk 2027 should be the first big event downtown with permanent bollards in place of trucks and a built-in power hookup in place of a generator, if Burke finishes on schedule. Until then, Prospect Avenue looks the way it always has. The new business on the block is a coffee shop that needed an extra year and three combined storefronts to reach its opening date.
Changes like these affect how a downtown block lives day to day, and that is part of how we think about value on the streets around it. If you own near Prospect or Park and want to know how the next two years could play into your plans, McCleary Group can walk you through it. Request your complimentary home valuation.